STEAM LINE 11barg MELAMIN KOČEVLJE
Object: STEAM LINE 11barg MELAMIN KOČEVLJE Investor: Melamin kemična tovarna d.d. Kočevje Phase: Final design Year: 2020 Project content: Project […]
Object: STEAM LINE 11barg MELAMIN KOČEVLJE Investor: Melamin kemična tovarna d.d. Kočevje Phase: Final design Year: 2020 Project content: Project […]
Object: STEAM LINE 4,5barg – MELAMIN KOČEVLJE Investor: Melamin kemična tovarna d.d. Kočevje Phase: Final design Year: 2019 Project content: […]
Object: REMOVAL OF METANOL FACTORY EQUIPMENT Investor: Methanol d.o.o. Phase: conceptual design, basic design for building permit Year: 2016-2017 Description […]
Object:: REMOVAL OF OIL TANKS Investor: GEA d.d. Phase: Conceptual design, basic design for building permit Year: 2013, 2014 Scope […]
Facility: BLOCK 6 in TE Šoštanj, COOLING AND SERVICE WATER, INSTRUMENTAL AND SERVICE AIR Investor: Šoštanj Thermal Power Plant d.o.o. […]
Object: TREMINAL FOR PETROLEUM PORT II Investor: PORT OF KOPER Phase: Final design Year: 2013 Project scope: Piping Stress and […]
PIPING ANALYSIS OF COMPRESSOR STATION ASME B31.3 pipeline analysis was performed for the needs of a foreign investor. Pipeline dimensions […]
Object: TANKS 500 m³, 250 m³ and 40 m³ for vegetable oil Investor: GEA Oil Factory d.d. Slovenska Bistrica Phase: […]
Object: STIRENA STORAGE V 300 TANK TANKS Investor: LUKA KOPER d.d. Phase: Final design, as built Year: 2012 SCOPE: Project […]
Object: COREX Gas based MIDREX DR Plant Phase: Final design Year: 2012 Project scope: PIPING ANALYSIS of piping systems for […]